Write down what ready means
For each package, identify the required access, information, previous work and materials. Record anything that is still uncertain. A supplier delivery date and a usable installation date may differ because unloading, storage or preparatory work must happen first.
If the package depends on client approval, create a decision activity rather than putting the question only in an installation note. Link the relevant task and review the deadline before committing labour. These small distinctions make contractor job planning more useful than a calendar entry alone.
Separate mobilisation, installation and completion
A job can require setup and protection before productive installation begins. It can also need testing, snagging or a handover after the main installation ends. Give these activities appropriate visibility rather than treating the last installation day as automatic completion.
For a bathroom refurbishment package, a sequence may include confirmation of specifications, material readiness, protection and strip-out, service work, inspections where applicable, finishes, installation, testing and handover. Adapt the sequence to the actual design and safe method; this example is not a technical instruction.
Keep a useful record of blockers
When a task cannot begin, mark it blocked and state the reason in plain language. “Awaiting approved specification” leads to a different follow-up from “area not available”. Review who is dealing with the issue and which later activities depend on its resolution.
The PlannerBuild overview lets you review activity status and related delivery, inspection and payment details. The Gantt shows how the work sits in time. Use both views to decide what needs attention; neither view can verify physical site readiness without your own checks.
Close the package deliberately
Record the actual completion date and progress. Review outstanding decisions, inspections and handover tasks before considering the package closed. If the scope has changed, make sure your contractual process records it; editing an activity is not itself an instruction or variation agreement.
For repeated types of work, keep a clean editable project backup as a starting reference and check every assumption when using it for a new job. Explore the demo to test your package structure. Full access depends on the plan displayed inside the application.
Questions about construction job planning
Is this a job booking or dispatch system?
The workspace supports construction activities and dates. It is not described as an automatic booking, route planning or workforce dispatch service.
Can I plan only one trade package?
Yes. A small package with clear prerequisites and handover checks can be a sensible first use of the project workspace.
Continue planning